Plainville Community School Linden Street School Building Committee Agendas & Minutes
August 11, 2005 Minutes
PLAINVILLE BOARD OF EDUCATION Committee Minutes Committee: Linden Street School Building Committee
Date: August 11, 2005 Time: 6:30 p.m. Attendees: George Iskra, Steve Martino, Mel Masse, Ron Pavano, Ken Prigodich, Becky Tyrrell, Barbara Willard, Rodney Wolfel Also Present: JCJ: Bill Mead, Downes Construction: Tom Castello, Paul Wojtowicz, Bemis Associates: Mark Bemis, BVH: Michael York, Technology: John Laskarzewski, Facilities: Steve Busel, Suzanne Greenbacker Absent: Ray Carroll, Dan Dube, Jack Mastrianni, Chairman Ken Prigodich called the meeting to order at 6:36 pm. RON PAVANO MADE A MOTION TO APPROVE THE MINUTES OF THE JULY 28, 2005 AND THE AUGUST 4, 2005 MEETINGS. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. Bill Mead gave an update on the project. He handed out the information requested for the plaque for the project. They are trying to add the Plainville Community Schools logo but it may not fit. He asked the members to review it to make sure all names were spelled correctly. The committee asked for a few corrections. One was to eliminate Suzanne Greenbacker’s name and that they put the names of the Linden Street Building Committee and the Plainville Community School’s Steering Committee in alphabetical order. RON PAVANO MADE A MOTION TOAPPROVE THE PLAQUE WITH THE CORRECTIONS. MEL MASSE SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. The committee discussed the playscape and how they need to be cautious regarding the underground drains. Bill Mead suggested that a representative from the playscape company go to the school and look at the site where the playscape will be located. Suzanne Greenbacker will contact the representative. Paul Wojtowicz from Downes Construction gave an update on the project. • The installation of the doors is almost completed. • The sheet rock and taping in the administrative area is done. • The pipe installation is done in the mechanical area. • The heat pipes have been installed in area 2. • Acoustical ceiling grids are in areas 2 and 3. • The acoustical wall panels were installed in the gymnasium and cafeteria. 1 of 6 • Temporary carpets are being installed in the classrooms. • The mill work is underway in area 2. • There is some masonry patching in the cafeteria area. • The elevator is in progress. • There is constant clean up on site going on everyday. • The above ceiling work in the cafeteria and serving area is completed. This will allow them to enclose the ceiling. • The sidewalks around the canopy area are being prepared. • The above ceiling inspection by Bemis Associates is ongoing. • They are installing the plumbing fixtures in area 1 and 2. • They are testing the fire alarm for the Fire Department. • They will be replacing the door to the cafeteria. • Back fill and grading has begun around the oil tank. Mel Masse will be able to get into the classrooms on August 22, 2005. Mike Midgette from Downes Construction has sent the information to the companies to have the chemicals put on the gymnasium and cafeteria floors. The shot blast was done last week and they will be retested. A relative humidity test will also be done. Mike York from BVH gave an update on the project. They are in the process of re-routing the data voice cable, they will pull it back to the second floor telecommunications room. This will make the installation much neater. Because of this they had to relocate an equipment rack on the second floor which will add electronics and cooling. This process is being approved through Bemis Associates. John Laskarzewski and Kevin Ross will add a data voice drop in the electrical room. They will install a security server, they are also requesting re-routing the existing fiber optic from the main office location to the storage room. The installation of the speakers and the speaker connections are in progress. Mr. York will coordinate installation of the projectors and smartboards with Emily Sledge from JCJ. Ron Pavano would like Mike York to speak with Jim Adams if he has any questions on the project. John Laskarzewski, Technology Consultant reported that everything is going great. He was asked about the absence of a smartboard and projector in particular rooms. Mr. Laskarzewski informed the committee that there would be a projector and a smartboard in every classroom. The committee was pleased with the update. At the next meeting John Laskarzewski will present the entire budget for approval from the committee. It then needs to be approved by the Board of Education and then go to SFU for approval. The projected budget for technology was $675,000. Suzanne Greenbacker asked if a drop down screen would be installed in the gymnasium. Bill Mead will look into having a screen put in the gym as it was not in the original specifications. Bill Mead from JCJ asked if a new timeline had been set up for deliveries of the FF&E. Mike Midgette from Downes is in the process of revising the timeline and should have it completed for the next meeting. 2 of 6 MEL MASSE MADE A MOTION TO PAY DOWNES CONSTRUCTION COMPANY FOR INVOICE #12 DATED AUGUST 10, 2005 THE SUM OF $882,874.00. RON PAVANO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. The breakdown is as follows: Downes Construction Company $67,440.00 Colossale Concrete, Inc. 99,401.00 D’Agostino 42,004.00 Shepard Steel 27,370.00 Universal Custom Millwork 73,223.00 Steeltech 7,599.00 Gold Seal Home Improvement 48,888.00 Ken Watterworth 2,850.00 A&J Caulking 16,593.00 Eastern Builders Hdwr 41,705.00 Cheviot Corporation 28,595.00 A&A Drywall , Inc. 43,976.00 Professional Floor covering, Inc. 11,943.00 Central Connecticut Acoustics 53,010.00 M. Frank Higgins 80,354.00 R&M Painting, LLC 25,901.00 Kitteredge Equip. 3,506.00 Bay State Elevator 6,228.00 IW&M 16,530.00 Ferguson Mechanical 121,131.00 Ferguson Electrical 64,627.00 _ Total of Requisition $882,874.00 MEL MASSE MADE A MOTION TO PAY JCJ FOR INVOICE DATED JULY 27, 2005 FOR ARCHITECTURAL SERVICES FROM JUNE 28, 2005 THROUGH JULY 24, 2005 THE SUM OF $8,440.05. RON PAVANO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. RON PAVANO MADE A MOTION TO APPROVE THE CHANGE ORDERS AS PRESENTED. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. Change Order Proposals: 1. COP No. 129: Ferguson Mechanical add check valves prior to PRV’s $703.00 On domestic Cold and Hot water systems 2. COP No. 147: Purchase new steam pot for kitchen $8,724.00 3. COP No. 148: New Quarry Tile in servery, old tile and concrete were in $5,024.00 unsatisfactory condition. Total add approx. $10,000.00 for concrete SOG removal and replacement. This is just for professional floor portion. 3 of 6 4. COP No. 149: Dedicated circuit to Ansul system, Feeder for KEF-1 from $12,466.00 KP1 to M1, replace existing KP1 feeder, replace panel KP Feeder, extern cooler and freezer circuits to emergency panel E2 5. COP No. 150: Colossale additional time for work to tie-in water lines. Existing lines not shown on drawings. $3,948.00
6. COP No. 151: Change entrances at overflow parking at west end of bus $3,485.00 turnaround for bituminous to concrete. 7. COP No. 152: Replace beam used for lintel at west end of K-wing. $883.00 Lintel at west end of K-wing was not shown on drawing. Shepard Steel. 8. COP No. 153: Modify lintel at courtyard, due to incorrect detail shown $835.00 on drawing. Shepard Steel Bill Mead asked if Downes Construction had seen the letter from the State of Connecticut regarding the approval of the change orders? Paul Wojtowicz said that letter was on Mike Midgette’s desk, Mike is on vacation this week. George Iskra asked for information regarding the noise from the air conditioning units on roof of the building. There was a complaint that the noise was very excessive. Ken Prigodich explained that they have requested a review from Ferguson and Trane to see if anything can be done. The committee is doing everything it can to accommodate the person involved. Discussion ensued regarding the noise. It will be put in the hands of the experts. Mr. Prigodich asked Suzanne Greenbacker if they can set up a time for the teachers to have a walkthrough of the new building prior to school starting. Sue is planning a time when this will happen. She will contact Ken or Ron in advance. Betty Boukus will also be invited. STEVE MARTINO MADE A MOTION TO ADJOURN THE MEETING. BARBARA WILLARD SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. The meeting was adjourned at 7:55 pm. The next meeting will be held on Thursday, August 25, 2005 at 6:30 pm in room 118 at the Plainville High School. Please contact Ken Prigodich or Tina Gryguc if you are unable to attend. Respectfully Submitted, Tina Gryguc Recording Secretary 4 of 6 MOTIONS MADE AT THE LINDEN STREET SCHOOL BUILDING COMMITTEE MEETING THURSDAY, AUGUST 11, 2005 RON PAVANO MADE A MOTION TO APPROVE THE MINUTES OF THE JULY 28, 2005 AND THE AUGUST 4, 2005 MEETINGS. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. RON PAVANO MADE A MOTION TOAPPROVE THE PLAQUE WITH THE CORRECTIONS. MEL MASSE SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY DOWNES CONSTRUCTION COMPANY FOR INVOICE #12 DATED AUGUST 10, 2005 THE SUM OF $882,874.00. RON PAVANO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. The breakdown is as follows: Downes Construction Company $67,440.00 Colossale Concrete, Inc. 99,401.00 D’Agostino 42,004.00 Shepard Steel 27,370.00 Universal Custom Millwork 73,223.00 Steeltech 7,599.00 Gold Seal Home Improvement 48,888.00 Ken Watterworth 2,850.00 A&J Caulking 16,593.00 Eastern Builders Hdwr 41,705.00 Cheviot Corporation 28,595.00 A&A Drywall , Inc. 43,976.00 Professional Floor covering, Inc. 11,943.00 Central Connecticut Acoustics 53,010.00 M. Frank Higgins 80,354.00 R&M Painting, LLC 25,901.00 Kitteredge Equip. 3,506.00 Bay State Elevator 6,228.00 IW&M 16,530.00 Ferguson Mechanical 121,131.00 Ferguson Electrical 64,627.00 _ Total of Requisition $882,874.00 MEL MASSE MADE A MOTION TO PAY JCJ FOR INVOICE DATED JULY 27, 2005 FOR ARCHITECTURAL SERVICES FROM JUNE 28, 2005 THROUGH JULY 24, 2005 THE SUM OF $8,440.05. RON PAVANO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. RON PAVANO MADE A MOTION TO APPROVE THE CHANGE ORDERS AS PRESENTED. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. 5 of 6 Change Order Proposals: 2. COP No. 129: Ferguson Mechanical add check valves prior to PRV’s $703.00 On domestic Cold and Hot water systems 2. COP No. 147: Purchase new steam pot for kitchen $8,724.00 3. COP No. 148: New Quarry Tile in servery, old tile and concrete were in $5,024.00 unsatisfactory condition. Total add approx. $10,000.00 for concrete SOG removal and replacement. This is just for professional floor portion. 4. No. 149: Dedicated circuit to Ansul system, Feeder for KEF-1 from $12,466.00 KP1 to M1, replace existing KP1 feeder, replace panel KP Feeder, extern cooler and freezer circuits to emergency panel E2 5. COP No. 150: Colossale additional time for work to tie-in water lines. Existing lines not shown on drawings. $3,948.00
6. COP No. 151: Change entrances at overflow parking at west end of bus $3,485.00 turnaround for bituminous to concrete. 7. COP No. 152: Replace beam used for lintel at west end of K-wing. $883.00 Lintel at west end of K-wing was not shown on drawing. Shepard Steel. 8. COP No. 153: Modify lintel at courtyard, due to incorrect detail shown $835.00 on drawings. Shepard Steel STEVE MARTINO MADE A MOTION TO ADJOURN THE MEETING. BARBARA WILLARD SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. 6 of 6
To view past agendas or minutes, please view our Archives. |