Plainville Community School Linden Street School Building Committee Agendas & Minutes
April 13, 2005 Minutes
PLAINVILLE BOARD OF EDUCATION Committee Minutes Committee: Linden Street School Building Committee Date: April 13, 2005 Time: 5:30 pm Attendees: Dan Dube, George Iskra, Jack Mastrianni, Mel Masse, Steve Martino, Ron Pavano, Ken Prigodich, Becky Tyrrell, Barbara Willard Also Present: JCJ: Bill Mead, Downes Construction: Paul Wojtowicz, Mike Midgette, Suzanne Greenbacker Absent: Ray Carroll, Rodney Wolfel Chairman Ken Prigodich called the meeting to order at 5:32 pm. RON PAVANO MADE A MOTION TO APPROVE THE MINUTES OF THE MARCH 24, 2005 MEETING. MEL MASSE SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. Bill Mead reported that he had a date to go to SFU (School Facilities Unit). A letter was given to Mr. Prigodich regarding that matter. He also reported that he met with Lucian Dragulski from Bemis Associates regarding the exposed piping through the Media Center and the ductwork in the gym. Discussion regarding this matter continued. Mike Midgette gave an update on the project. In Area 1: • The Kindergarten wing exterior brick is done and the tarps were removed. • The interior Kindergarten wing is completed and painting will begin next week. • The ceiling grids are complete, lights and sprinkler drops will also be installed. • Windows will be installed during the week of 4/18/05. In Area 2: • On the first floor 80% of the MEP is complete. • Block work is 95% complete on the 1st floor. • Exterior brick work is 30 % completed. • The 2nd floor is 30 % complete. • Ferguson Mechanical is installing large ducts in the corridors. This has slowed things down slightly. • In the gym, there is an 80% slab on grade which has been removed. They will begin the ramps on the north side of the gym and construct a retaining wall. • Cafeteria work has also begun. Mr. Midgette reported that next week when the students are on vacation they will begin abatement in the cafeteria and the server area. They will also begin Hazmat in the gym where the temporary wall is located. Mel Masse is concerned about the shelving in the kitchen area closet. He wants to make sure it doesn’t get thrown out. Next week Mr. Pavano and Mr. Masse will do a walk through to see what needs to be kept. Paul Wojtowicz from Downes Construction feels there will be plenty of time before Manafort Brothers begins demolition. 1 of 5 Bill Mead stated that the Linden project is beginning to come together. You can actually see how the project is beginning to look. The lobby is defined, the bus turn-around is near completion, curbs are installed and the center sidewalk is complete. The Committee is very happy with the progress of the project. Mr. Pavano will make himself available to anyone who would like to tour the school. Please contact him for a tour if you are interested. Ron Pavano spoke to Suzanne Greenbacker regarding parents parking in ‘no parking zones’ in front of the school. She told the committee that she has taken a great deal of abuse from parents regarding this matter. She has sent home many letters and still the illegal parking continues. Ron Pavano said that the reason the signs were in place was to remove the traffic from the streets to protect the children. Mel Masse stated that it is nearly impossible to get down Linden Street at certain times with the cars parked on both sides. The committee is concerned about kids and safety. Ken Prigodich would like to be contacted if she has any further problems. MEL MASSE MADE A MOTION TO PAY DOWNES CONSTRUCTION FOR INVOICE #8 DATED APRIL 11, 2005 THE AMOUNT OF $1,786,509.00. JACK MASTRIANNI SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. THE BREAKDOWN IS AS FOLLOWS: DOWNES CONSTRUCTION CO. LLC $ 67,440.00 COLOSSALE CONCRETE, INC. 44,175.00 MANAFORT BROS. 13,783.00 SHEPARD STEEL 49, 970.00 D’AGOSTINO 754,802.00 STEELTECH BUILDING PRODUCTS, INC. 31,573.00 GOLD SEAL HOME IMPROVEMENTS 65,597.00 EASTERN BUILDERS HDWR. 12,160.00 KEN WATTERWORTH, INC. 27,835.00 A&A DRYWALL 74,850.00 PROFESSIONAL FLOOR COVERING, INC. 30,238.00 KITTEREDGE EQUIP. 15,698.00 IW&M 17,670.00 FERGUSON MECHANICAL 500,844.00 FERGUSON ELECTRICAL 79,874.00 MEL MASSE MADE A MOTION TO PAY INDEPENDENT MATERIALS TESTING LABORATORIES, INC FOR INVOICE #6729-M DATED MARCH 28, 2005 THE AMOUNT OF $3,363.00. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY COMPLETE WASTE REMOVAL & RECYCLING SERVICES FOR INVOICE #53X0016 DATED MARCH 31, 2005 THE AMOUNT OF $4,941.62. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY COMPLETE WASTE REMOVAL & RECYCLING SERVICES FOR INVOICE #53L00053 DATED MARCH 21, 2005 THE AMOUNT OF $4,100.34. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY JCJ FOR INVOICE #20 DATED APRIL 11, 2005 THE AMOUNT OF $16,006.47 FOR ARCHITECTURAL SERVICES FROM MARCH 7, 2005 THROUGH APRIL 10, 2005. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. 2 of 5 ADDITIONS AND RENOVATIONS CHANGE ORDERS TO BE REVIEWED
1. FERGUSON ELECTRIC: • COP NO. 27 ELEVATOR SHUNT TRIP FOR FIRE ALARM $1,693.00 • COP NO. 49 POWER FOR LIGHTS IN DISPLAY CASES $1,725.00 • COP NO. 38 GFI OUTLET FOR RTU-3-1 $$1,394.00 2. SHEPARD STEEL, MISCELLANEOUS METALS • COP NO. 56 ADD RAILING AT GYM ROOF AT RTU $4,207.00 • COP NO. 77 INSTALL STEEL FRAME SUPPORT AT K-WING RTU $3,313,00 • COP NO. 82 K-WING W.ENTRANCE LINTEL SEATS $360.00 3. FERGUSON MECHANICAL • COP NO. ROOF CURBS FOR CU-2-1 $527.00 Discussion regarding Change Orders ensued. RON PAVANO MADE A MOTION TO THE APPROVE CHANGE ORDERS AS PRESENTED. MEL MASSE SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. Mike Midgette from Downes Construction will have a better feel for the percent of change orders for the project by the next meeting. Dan Dube has requested that Downes Construction lump all the change orders that pertain to a particular part of the project together. Discussion continued regarding how change orders are processed. Michael York from BVH will stop by the project to look at the access wiring. At the next meeting, Paul Wojtowicz from Downes Construction will have a complete write up for the portion of the roof that needs to be replaced. The next meeting is scheduled for Thursday, April 28, 2005 at 6:30 pm in the Linden Street School Library. JACK MASTRIANNI MADE A MOTION TO ADJOURN THE MEETING. BARBARA WILLARD SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. The meeting was adjourned at 6:15 pm. Respectfully Submitted, Tina Gryguc Recording Secretary 3 of 5 MOTIONS MADE AT THE LINDEN STREET SCHOOL BUILDING COMMITTEE MEETING THURSDAY, APRIL 13, 2005 RON PAVANO MADE A MOTION TO APPROVE THE MINUTES OF THE MARCH 24, 2005 MEETING. MEL MASSE SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY DOWNES CONSTRUCTION FOR INVOICE #8 DATED APRIL 11, 2005 THE AMOUNT OF $1,786,509.00. JACK MASTRIANNI SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. THE BREAKDOWN IS AS FOLLOWS: DOWNES CONSTRUCTION CO. LLC $ 67,440.00 COLOSSALE CONCRETE, INC. 44,175.00 MANAFORT BROS. 13,783.00 SHEPARD STEEL 49, 970.00 D’AGOSTINO 754,802.00 STEELTECH BUILDING PRODUCTS, INC. 31,573.00 GOLD SEAL HOME IMPROVEMENTS 65,597.00 EASTERN BUILDERS HDWR. 12,160.00 KEN WATTERWORTH, INC. 27,835.00 A&A DRYWALL 74,850.00 PROFESSIONAL FLOOR COVERING, INC. 30,238.00 KITTEREDGE EQUIP. 15,698.00 IW&M 17,670.00 FERGUSON MECHANICAL 500,844.00 FERGUSON ELECTRICAL 79,874.00 MEL MASSE MADE A MOTION TO PAY INDEPENDENT MATERIALS TESTING LABORATORIES, INC FOR INVOICE #6729-M DATED MARCH 28, 2005 THE AMOUNT OF $3,363.00. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY COMPLETE WASTE REMOVAL & RECYCLING SERVICES FOR INVOICE #53X0016 DATED MARCH 31, 2005 THE AMOUNT OF $4,941.62. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY COMPLETE WASTE REMOVAL & RECYCLING SERVICES FOR INVOICE #53L00053 DATED MARCH 21, 2005 THE AMOUNT OF $4,100.34. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. MEL MASSE MADE A MOTION TO PAY JCJ FOR INVOICE #20 DATED APRIL 11, 2005 THE AMOUNT OF $16,006.47 FOR ARCHITECTURAL SERVICES FROM MARCH 7, 2005 THROUGH APRIL 10, 2005. STEVE MARTINO SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. ADDITIONS AND RENOVATIONS CHANGE ORDERS TO BE REVIEWED 4. FERGUSON ELECTRIC: • COP NO. 27 ELEVATOR SHUNT TRIP FOR FIRE ALARM $1,693.00 • COP NO. 49 POWER FOR LIGHTS IN DISPLAY CASES $1,725.00 • COP NO. 38 GFI OUTLET FOR RTU-3-1 $$1,394.00 4 of 5 5. SHEPARD STEEL, MISCELLANEOUS METALS • COP NO. 56 ADD RAILING AT GYM ROOF AT RTU $4,207.00 • COP NO. 77 INSTALL STEEL FRAME SUPPORT AT K-WING RTU $3,313,00 • COP NO. 82 K-WING W.ENTRANCE LINTEL SEATS $360.00 6. FERGUSON MECHANICAL • COP NO. ROOF CURBS FOR CU-2-1 $527.00 RON PAVANO MADE A MOTION TO THE APPROVE CHANGE ORDERS AS PRESENTED. MEL MASSE SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. JACK MASTRIANNI MADE A MOTION TO ADJOURN THE MEETING. BARBARA WILLARD SECONDED THE MOTION. THE MOTION PASSED UNANIMOUSLY. 5 of 5
To view past agendas or minutes, please view our Archives. |